Brief:
Drive cost out of all areas of existing fixtures and installation


Example solutions:

Reduce

  • Simplified unitary / eliminated left and right-handed units .
  • Amended certain dimensions slightly to increase sheet yield
  • Re-designed centre floor ‘Welcome’ unit from ceiling-fixed to floor-fixed
  • Reduced number of Parts by 30%
  • Introduced foil wrap technology and pre-faced materials to simplify production
  • Incorporated graphics onto system backpanels

Benefits

  • Reduced equipment costs by over 50%
  • Reduced leadtimes through Kanban methodology